Daylighting Dandenong Creek Project
Date of Event : Tue Jan 23, 2018 12:17AM

Happy 2018 to Everyone!

You will be pleased to hear that works have now commenced on the much anticipated
Daylighting Dandenong Creek Project.
It has been a busy start to the year for the project, with the following already accomplished;
? Project site temporary office established
? Temporary safety fencing installed along the perimeter of the project site
? Commencement of ground excavation within the creek bed
? Installation of Project signage

WHATS COMING UP?

Upcoming works will see the temporary detour of the Shared User Path. Signs are in place at
both ends of the detour advising cyclists and pedestrians of the upcoming detour that begins
on Wednesday the 24th of January. This detour will be in place for the duration of the project.
Please see below for detailed map. Feel free to share this map that details the path detour.
Again we would like to thank you for your understanding and patience.
We will keep you updated regularly as the project progresses but please feel free to get in
touch – we would love to hear from you!

 